Element 1. Policy |
|
Implementation
Task/Activity |
Primary
Responsibility |
Schedule/Status |
Comments |
|
Accomplish
further internal communication of the policy statement by
posting the policy statement to bulletin boards and through
continued meetings and trainings. |
EMS Coordinator
EMS Core Team |
Completed-maintain conformance |
|
Element 2. Environmental
Requirements
|
|
Implementation
Task/Activity |
Primary
Responsibility |
Schedule/Status |
Comments |
|
Update, as new Environmental
Requirements are adopted/implemented. |
EMS Core Team |
Completed-maintain conformance |
|
Elements 3 & 4. Practices,
Aspects, Impacts and Risk Prioritization
|
|
Implementation
Task/Activity |
Primary
Responsibility |
Schedule/Status |
Comments |
|
Continue to monitor and adjust
identified practices, aspects, impacts and risks as activities
and processes change. |
EMS Coordinator
EMS Core Team |
Completed-maintain conformance |
|
Elements 5. Environmental
Objectives and Targets
|
|
Implementation
Task/Activity |
Primary
Responsibility |
Schedule/Status |
Comments |
|
Implement POA&Ms for objectives
and targets.
Monitor objectives and targets
to ensure that targets are being met. |
EMS Core Team
|
Completed - maintain conformance |
|
Element 6. Actions to Improve
Performance
|
|
Implementation
Task/Activity |
Primary
Responsibility |
Schedule/Status |
Comments |
|
Implement set objectives and
targets for aspects that are identified
Identify administrative or
behavioral improvements.
Identify necessary funding to
achieve objectives and targets. |
EMS Coordinator
EMS Core Team
EMS Core Team
|
Completed-maintain conformance |
|
|
Completed-maintain conformance |
|
Element 7. Structure,
Responsibilities and Programs
|
|
Implementation
Task/Activity |
Primary
Responsibility |
Schedule/Status |
Comments |
|
Establish working relationship on
EMS Develop and maintain
EMS participants working relationship to establish communication
between practice owners and EMS Core Team
EMS Core Team work with EMS
Management Review Team to communicate roles and responsibilities |
EMS Core Team |
Completed-maintain conformance |
|
Element 8. Funding and
Manpower
|
|
Implementation
Task/Activity |
Primary
Responsibility |
Schedule/Status |
Comments |
|
Identify
objectives and targets needing funding
Evaluate
manpower to ensure that it is appropriate to meet objectives and
targets. |
EMS Core Team
EMS Core Team |
Projects currently in
progress - see element 5 |
|
|
Completed - maintain
conformance |
|
Element 9. Training
|
|
Implementation
Task/Activity |
Primary
Responsibility |
Schedule/Status |
Comments |
|
Provide EMS
training to Practice Owners associated with Objectives and
Targets. |
EMS Core Team |
EMS training provided during each training event |
|
Element 10. Communication
|
|
Implementation
Task/Activity |
Primary
Responsibility |
Schedule/Status |
Comments |
|
Identify procedures that need to
be implemented. |
EMS Core Team |
Completed - maintain conformance |
|
Element 11. Emergency
Preparedness and Response
|
|
Implementation
Task/Activity |
Primary
Responsibility |
Schedule/Status |
Comments |
|
Ensure that new practices are
included in the Emergency Preparedness and Response documents |
EMS Coordinator
EMS Core Team |
Completed - maintain conformance |
|
Element 12. Document and
Record Control
|
|
Implementation
Task/Activity |
Primary
Responsibility |
Schedule/Status |
Comments |
|
Identify records and documents
Designate a location for
document maintenance and recordkeeping
Ensure all records are updated
Purge obsolete records |
EMS Core Team
|
Completed - maintain conformance |
|
Element 13. Environmental SOPs
|
|
Implementation
Task/Activity |
Primary
Responsibility |
Schedule/Status |
Comments |
|
Develop SOPs for each practice.
Prioritize SOPs for practices
associated with Objectives and Targets.
Identify POCs responsible for
practice SOPs
Provide training on SOP for
Practice Owners. |
EMS Core Team |
Completed - maintain conformance |
|
Element 14. EMS Document
|
|
Implementation
Task/Activity |
Primary
Responsibility |
Schedule/Status |
Comments |
|
Brief IC and
obtain approval of EMS Document |
EMS Core Team |
Completed - maintain conformance |
|
Element 15. Monitoring and
Measurement
|
|
Implementation
Task/Activity |
Primary
Responsibility |
Schedule/Status |
Comments |
|
Update
self-audit checklist
Track objective
and target progress |
EMS Core Team |
Completed - maintain conformance |
|
Element 16. Problem Solving
|
|
Implementation
Task/Activity |
Primary
Responsibility |
Schedule/Status |
Comments |
|
Document problem solving efforts |
EMS Core Team |
Completed - maintain conformance |
|
Element 17. EMS Review
|
|
Implementation
Task/Activity |
Primary
Responsibility |
Schedule/Status |
Comments |
|
Conduct EMS
self-audit |
EMS Coordinator |
Completed - maintain conformance |
|
Element 18. Management Review
|
|
Implementation
Task/Activity |
Primary
Responsibility |
Schedule/Status |
Comments |
|
Conduct a meeting with the EMS
Core Team and EMS Management Review Team
Conduct EMS Management Review Team
meeting to determine conformance with the 2007 conformance
deadline. |
EMS Core Team
EMS Mgt. Review Team |
Completed - maintain conformance |
|